Date | Updates |
31.01.2012 - 31.03.2012
| - Mobilization, area set up, area management, establishment of area control system, allocation of equipment and other general stuff;
- Provision and agreement of the construction material with SOFAZ
|
30.04.2012 | - Construction-assembly works on the 1st floor of two storey mezzaine floor are going on. Construction-assembly works on the ground of the 2nd floor are going on.
|
31.05.2012 | - Construction-assembly works of the 2nd floor are finished. Construction-assembly works of the 3rd floor are continuing.
|
30.06.2012 | - Construction-assembly works of the 3rd floor are finished. Construction-assembly works are going on the columns and walls of the 4th floor.
|
31.07.2012 | - Construction-assembly works of the 4th , 5th and 6th floors are finished. Construction-assembly works are going on the 7th floor.
|
31.08.2012 | - Construction-assembly works of the 7th, 8th and 9th floors are finished. Construction-assembly works of the tenth floor are going on;
- Painting works are going on in the basement.
|
30.09.2012 | - Construction-assembly works on the 10th and 11th floors are finished. Construction-assembly works of the 12th floor are going on;
- Painting works are going on in the basement;
- Mechanical, electrical and plumbing works are going on in the basement and standard floors.
|
31.10.2012 | - Construction-assembly works on the 12th and 13th floors are finished. Construction-assembly works of the 14th floor are going on;
- Painting works are going on in the basement;
- Ceiling construction of the parking space on the -2nd floor is finished;
- Mechanical, electrical and plumbing works are going on in the basement and standard floors.
|
30.11.2012 | - Construction-assembly works on the 14th, 15th , 16th and 17th floors are finished. Construction-assembly works of the 18th floor are going on;
- Painting works are going on in the basement;
- Cladding and plastering works of the 6-10th floors are going on;
- Ventilation duct works and construction of plumbing pipes are going on in the basement and standard floors.
|
31.12.2012 | - Construction-assembly works on the 18th and 19th floors are finished. Construction-assembly works of the 20th floor are going on;
- Painting works are going on in the basement;
- Cladding and plastering works of the 6-10th floors are going on;
- Construction of pipes and fancoils in the basement and standard floors are going on.
|
31.01.2013 | - Painting works are going on in the basement;
- Construction of pipes and fancoils in the basement and standard floors are going on.
- Temporary facade construction-assembly works are going on.
|
28.02.2013 | - Painting works are going on in the basement;
- Construction of pipes and fancoils in the basement and standard floors are going on;
- Temporary facade construction-assembly works are going on.
|
30.03.2013 | - Temporary facade construction-assembly works are going on;
- Construction works are being continued is basement and standard floors;
- Azeri steel metal construction works are going on. Modul 2 is being installed.
|
30.04.2013 | - Temporary facade construction-assembly works are going on;
- Construction works are being continued is basement and standard floors;
- Azeri steel metal construction works are going on. Modul 2 is being installed.
|
30.05.2013 | - Facade consturction works on floors L1, L2, L3, L4 are going on;
- Glass panels for facade are being constructed on floors L5, L6, L7, L8, L9, L10, L11, L12, L14
- Azeri steel metal construction works are going on. Modul 2 (Part C) is being istalled. Totally 9 parts are installed.
|
30.06.2013 | - Concrete surface finishing works on floors L12- L21 are going on;
- Construction of glass panels are continuing;
- Cladding and waterproofing works are going on.
|
31.07.2013 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Construction of glass panels on floors L1 – L3 are about to be completed.
|
31.08.2013 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Construction of glass panels are going on;
- Installation of the boiler room is going on;
- Installation of doors have started on floor B1.
|
30.09.2013 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Construction of glass panels on floors L1-L3 are finished;
- Installation of the boiler room is going on;
- Installation of doors has started on floor B1.
|
31.10.2013 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Decoration works on facade are going on;
- Installation of facade panels are going on;
- Installation of boiler room is going on.
|
30.11.2013 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Installation of facade panels are going on;
- Decoration works on facade are going on;
- Installation of facade panels on floor L3 is being finished;
- Marble installation works on floors are going on.
|
31.12.2013 | - Marble installation works on floors are going on;
- Installation of boiler room is going on;
- Decoration works on facade are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Installation of doors on floor B1 is going on.
|
31.01.2014 | - Marble installation works on floors are going on;
- Decoration works on facade are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Installation of doors on floor B1 is going on.
|
28.02.2014 | - Marble installation works on floors are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Construction of gypsum plasterboard works on floors L8 – L18 are going on;
- Installation of boiler room is going on.
|
31.03.2014 | - Marble installation works on floors are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Furniture installation works on floors L7, L8 are going on;
- Marble installation works of the indoor pool are completed;
- Landscaping works are going on around the building.
|
30.04.2014 | - Concrete surface finishing works on floors L12 – L21 are going on;
- Cleaning works on floors L8-L12 are carried out;
- Furniture installation works on floors L8-L12 are going on;
- Parquet installation works on floor L21 are carried out;
- Landscaping works are going on around the building.
|
31.05.2014 | - Parquet installation works on floor L1 are going on;
- Furniture installation works on floors L8-L12 are going on;
- Parquet installation works on floor L21are completed;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Landscaping works are going on around the building.
|
30.06.2014 | - Parquet installation works on floor L1 are going on;
- Furniture installation works on floors L8-L12 are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Landscaping works are going on around the building.
|
31.07.2014 | - Parquet installation works on floor L1 are going on;
- Furniture installation works on floors L8-L12 are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Landscaping works are going on around the building.
|
31.08.2014 | - Furniture installation works on floors L8-L12 are going on;
- Concrete surface finishing works on floors L12 – L21 are going on;
- Epoxy coating of the pool on floor B1 has started;
- Landscaping works are going on around the building.
|
30.09.2014 | - Cleaning works on floors L8-L21 are carried out;
- Facade lighting installation works on floor L4 are going on;
- Landscaping works around the building are going on.
|
31.10.2014 | - Cleaning works on floors L1-L21 are carried out;
- Facade lighting installation works on floor L4 are going on;
- Landscaping works around the building are going on.
|