INFORMATION ON ONGOING CONSTRUCTION-ASSEMBLY WORKS AT THE NEW ADMINISTRATIVE BUILDING OF THE STATE OIL FUND OF THE REPUBLIC OF AZERBAIJAN

 

State Oil Fund has signed a contract with Besix-Az Besix Consortium on construction of the new administrative building on December 20, 2011.

 

Update table (monthly):

 


DateUpdates

31.01.2012 - 31.03.2012


  • Mobilization, area set up, area management, establishment of area control system, allocation of equipment and other general stuff;
  • Provision and agreement of the construction material with SOFAZ

30.04.2012

  • Construction-assembly works on the 1st  floor of two storey mezzaine floor are going on. Construction-assembly works on the ground of the 2nd  floor are going on.

31.05.2012

  • Construction-assembly works of the 2nd  floor are finished. Construction-assembly works of the 3rd  floor are continuing.

30.06.2012

  • Construction-assembly works of the 3rd floor are finished. Construction-assembly works are going on the columns and walls of the 4th floor.

31.07.2012

  • Construction-assembly works of the 4th , 5th  and 6th  floors are finished. Construction-assembly works are going on the 7th  floor.

31.08.2012

  • Construction-assembly works of the 7th, 8th  and 9th  floors are finished. Construction-assembly works of the tenth floor are going on;
  • Painting works are going on in the basement.

30.09.2012

  • Construction-assembly works on the 10th  and 11th  floors are finished. Construction-assembly works of the 12th  floor are going on;
  • Painting works are going on in the basement;
  • Mechanical, electrical and plumbing works are going on in the basement and standard floors.

31.10.2012

  • Construction-assembly works on the 12th  and 13th  floors are finished. Construction-assembly works of the 14th floor are going on;
  • Painting works are going on in the basement;
  • Ceiling construction of the parking space on the -2nd floor is finished;
  • Mechanical, electrical and plumbing works are going on in the basement and standard floors.

30.11.2012

  • Construction-assembly works on the 14th, 15th , 16th  and 17th  floors are finished. Construction-assembly works of the 18th  floor are going on;
  • Painting works are going on in the basement;
  • Cladding and plastering works of the 6-10th floors are going on;
  •  Ventilation duct works and construction of plumbing pipes are going on in the basement and standard floors.

31.12.2012

  • Construction-assembly works on the 18th  and 19th floors are finished. Construction-assembly works of the 20th  floor are going on;
  • Painting works are going on in the basement;
  • Cladding and plastering works of the 6-10th floors are going on;
  • Construction of pipes and fancoils in the basement and standard floors are going on.

31.01.2013

  •  Painting works are going on in the basement;
  •  Construction of pipes and fancoils in the basement and standard floors are going on.
  •  Temporary facade construction-assembly works are going on.

28.02.2013 

  • Painting works are going on in the basement;
  • Construction of pipes and fancoils in the basement and standard floors are going on;
  • Temporary facade construction-assembly works are going on.

30.03.2013

  • Temporary facade construction-assembly works are going on;
  • Construction works are being continued is basement and standard floors;
  • Azeri steel metal construction works are going on. Modul 2 is being installed.

30.04.2013

  • Temporary facade construction-assembly works are going on;
  • Construction works are being continued is basement and standard floors;
  •  Azeri steel metal construction works are going on. Modul 2 is being installed.

30.05.2013

  • Facade consturction works on floors L1, L2, L3, L4 are going on;
  •  Glass panels for facade are being constructed on floors L5, L6, L7, L8, L9, L10, L11, L12, L14
  •  Azeri steel metal construction works are going on. Modul 2 (Part C) is being istalled. Totally 9 parts are installed.

30.06.2013

  • Concrete surface finishing works on floors L12- L21 are going on;
  • Construction of glass panels are continuing;
  • Cladding and waterproofing works are going on.

31.07.2013

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Construction of glass panels on floors L1 – L3 are about to be completed.

31.08.2013

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Construction of glass panels are going on;
  • Installation of the boiler room is going on;
  • Installation of doors have started on floor B1.

30.09.2013

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Construction of glass panels on floors L1-L3 are finished;
  • Installation of the boiler room is going on;
  • Installation of doors has started on floor B1.

 

31.10.2013

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Decoration works on facade are going on;
  • Installation of facade panels are going on;
  • Installation of boiler room is going on.

30.11.2013

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Installation of facade panels are going on;
  • Decoration works on facade are going on;
  • Installation of facade panels on floor L3 is being finished;
  • Marble installation works on floors are going on.

31.12.2013

  • Marble installation works on floors are going on;
  • Installation of boiler room is going on;
  • Decoration works on facade are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Installation of doors on floor B1 is going on.

31.01.2014

  • Marble installation works on floors are going on;
  • Decoration works on facade are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Installation of doors on floor B1 is going on.

28.02.2014

  • Marble installation works on floors are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Construction of gypsum plasterboard works on floors L8 – L18 are going on;
  • Installation of boiler room is going on.

31.03.2014

  • Marble installation works on floors are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Furniture installation works on floors L7, L8 are going on;
  • Marble installation works of the indoor pool are completed;
  • Landscaping works are going on around the building.

30.04.2014

  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Cleaning works on floors L8-L12 are carried out;
  • Furniture installation works on floors L8-L12 are going on;
  • Parquet installation works on floor L21 are carried out;
  • Landscaping works are going on around the building.

31.05.2014

  • Parquet installation works on floor L1 are going on;
  • Furniture installation works on floors L8-L12 are going on;
  •  Parquet installation works on floor L21are completed;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Landscaping works are going on around the building.

30.06.2014

  • Parquet installation works on floor L1 are going on;
  • Furniture installation works on floors L8-L12 are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Landscaping works are going on around the building.

31.07.2014

  • Parquet installation works on floor L1 are going on;
  • Furniture installation works on floors L8-L12 are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Landscaping works are going on around the building.

31.08.2014

  • Furniture installation works on floors L8-L12 are going on;
  • Concrete surface finishing works on floors L12 – L21 are going on;
  • Epoxy coating of the pool on floor B1 has started;
  • Landscaping works are going on around the building.

30.09.2014

  • Cleaning works on floors L8-L21 are carried out;
  • Facade lighting installation works on floor L4 are going on;
  • Landscaping works around the building are going on.

31.10.2014

  • Cleaning works on floors L1-L21 are carried out;
  • Facade lighting installation works on floor L4 are going on;
  • Landscaping works around the building are going on.